Project Controls

Governance control room across every project type in the portfolio.

Projects in Scope
9
Gates Tracked
10
Open Risks
58
Critical Risks
7
Pending Approvals
30
Pending Decisions
11

Filters

Stage Gate Status

10 gates across the portfolio

ProjectTypeGatePlannedStatusCriteria completeDecision
National GIS Platform ImplementationGISData Model Approval2026-06-01Approved2/2Approved 2026-06-12
National GIS Platform ImplementationGISSpatial QA Sign-off2026-11-28In Review1/4
Oracle Fusion ERP TransformationERPFit-Gap Sign-off2026-04-30Approved2/2Approved by Steering Committee on 2026-05-08
Oracle Fusion ERP TransformationERPSIT Readiness2026-08-14Approved1/2Approved with 2 conditions
Oracle Fusion ERP TransformationERPCutover Readiness2026-12-18Blocked1/6
Hospital Facilities Maintenance ProgramFacilitiesPPM Baseline2026-05-15Approved2/2Approved 2026-05-15
Hospital Facilities Maintenance ProgramFacilitiesContract Review2026-09-30In Review1/3
Cybersecurity Infrastructure UpgradeITSIT Readiness2026-10-16Pending1/2
New Administrative Building ProjectConstructionExecution Start2026-04-30Approved2/2Approved 2026-04-28
New Administrative Building ProjectConstructionBCC — Building Completion2028-04-30Pending0/2

Portfolio Cost Exposure

Approved vs forecast vs committed

Approved
QAR 590.70 M
Forecast
QAR 600.40 M
Committed
QAR 386.72 M
Spent
QAR 175.89 M