AR

New Administrative Building Project

ETP-2026-005 · Construction Project · Stage-gate · Lusail, Qatar

Sponsor Ahmed Al RashidPM Ibrahim DohaPMO Group PMO — Omar SiddiquiContractor Al Bidda ContractingDates 2026-02-152028-06-30Budget QAR 365.00 M
Under ConstructionNext gate: BCC — Building CompletionAMBER
Gates
2
Approved
1
In Review
0
Blocked
0

Execution Start

Planned 2026-04-30

Approved
Mobilisation complete
Evidence: Mobilisation report
complete
HSE plan approved
Evidence: HSE-Plan-R2.pdf
complete

BCC — Building Completion

Planned 2028-04-30

Pending
Snag list closed
incomplete
Testing complete
incomplete