New Administrative Building Project
ETP-2026-005 · Construction Project · Stage-gate · Lusail, Qatar
Sponsor Ahmed Al RashidPM Ibrahim DohaPMO Group PMO — Omar SiddiquiContractor Al Bidda ContractingDates 2026-02-15 → 2028-06-30Budget QAR 365.00 M
Under ConstructionNext gate: BCC — Building CompletionAMBER
Gates
2
Approved
1
In Review
0
Blocked
0
Execution Start
Planned 2026-04-30
Mobilisation complete
Evidence: Mobilisation report
HSE plan approved
Evidence: HSE-Plan-R2.pdf
BCC — Building Completion
Planned 2028-04-30
Snag list closed
Testing complete