National GIS Platform Implementation
ETP-2026-001 · GIS Implementation · Hybrid · Doha, Qatar
Sponsor Dr. Fatima Al MansooriPM Yousef RahmanPMO Group PMO — Omar SiddiquiImplementation Partner GeoSphere SystemsDates 2026-02-02 → 2027-06-30Budget QAR 26.50 M
Data Cleansing & MigrationNext gate: Spatial QA Sign-offAMBER
Gates
2
Approved
1
In Review
1
Blocked
0
Data Model Approval
Planned 2026-06-01
Logical model approved
Evidence: GDL-007 R-3
Coordinate system agreed
Evidence: QND95 / UTM 39N
Spatial QA Sign-off
Planned 2026-11-28
Topology validation passed
Evidence: 11 open DQ issues
Accuracy tolerance met
Evidence: 0.28 m RMSE
Attribute completeness > 98%
Evidence: 96.4%
Performance test passed
Evidence: Deferred to deployment gate