National GIS Platform Implementation

ETP-2026-001 · GIS Implementation · Hybrid · Doha, Qatar

Sponsor Dr. Fatima Al MansooriPM Yousef RahmanPMO Group PMO — Omar SiddiquiImplementation Partner GeoSphere SystemsDates 2026-02-022027-06-30Budget QAR 26.50 M
Data Cleansing & MigrationNext gate: Spatial QA Sign-offAMBER
Gates
2
Approved
1
In Review
1
Blocked
0

Data Model Approval

Planned 2026-06-01

Approved
Logical model approved
Evidence: GDL-007 R-3
complete
Coordinate system agreed
Evidence: QND95 / UTM 39N
complete

Spatial QA Sign-off

Planned 2026-11-28

In Review
Topology validation passed
Evidence: 11 open DQ issues
incomplete
Accuracy tolerance met
Evidence: 0.28 m RMSE
complete
Attribute completeness > 98%
Evidence: 96.4%
incomplete
Performance test passed
Evidence: Deferred to deployment gate
waived