AR

Oracle Fusion ERP Transformation

ETP-2026-002 · Oracle ERP Implementation · Hybrid · Doha, Qatar

Sponsor Ahmed Al RashidPM Layla HaddadPMO Group PMO — Omar SiddiquiImplementation Partner Meridian Consulting (Oracle Partner)Dates 2026-01-122027-03-31Budget QAR 48.20 M
System Integration TestingNext gate: Cutover ReadinessRED
Gates
3
Approved
2
In Review
0
Blocked
1

Fit-Gap Sign-off

Planned 2026-04-30

Approved
Gap decisions approved
Evidence: SC-Minutes-04.pdf
complete
Extension list frozen
Evidence: EXT-Register-v2.xlsx
complete

SIT Readiness

Planned 2026-08-14

Approved
Interfaces built
Evidence: INT-Build-Report.pdf
complete
Conversion trial load 2 complete
Evidence: Waiver-TL2.pdf
waived

Cutover Readiness

Planned 2026-12-18

Blocked
Cutover plan approved
Evidence: DL-024 in review
incomplete
Final conversion reconciliation
Evidence: Trial Load 3 slipped
blocked
Rollback rehearsed
incomplete
Open P1 defects = 0
Evidence: 6 critical defects open
blocked
Business sign-off — Finance
incomplete
Command centre roster
Evidence: Roster-v1.xlsx
complete