AR

National GIS Platform Implementation

ETP-2026-001 · GIS Implementation · Hybrid · Doha, Qatar

Sponsor Dr. Fatima Al MansooriPM Yousef RahmanPMO Group PMO — Omar SiddiquiImplementation Partner GeoSphere SystemsDates 2026-02-022027-06-30Budget QAR 26.50 M
Data Cleansing & MigrationNext gate: Spatial QA Sign-offAMBER
Completion
38%
Planned 40%
Phase
Data Cleansing & Migration
Next gate Spatial QA Sign-off
Forecast vs Budget
QAR 26.90 M
Approved QAR 26.50 M
Pending Approvals
4
Open Risks
9
1 critical
Resource Utilisation
74%
Datasets Inventoried
92%
Layers Migrated
46%
Spatial Quality Score
81%
Services Deployed
14
Open Data-Quality Issues
11
UAT Completion
0%

Phase Progress

Planned vs actual by lifecycle phase

Progress Curve

Planned, actual and forecast %

Stage Gate Timeline

Data Model Approval
Planned 2026-06-01
2/2Approved
Spatial QA Sign-off
Planned 2026-11-28
1/4In Review

Milestone Performance

Dataset Inventory Sign-off
Data Inventory · Yousef Rahman
Completed
2026-04-152026-04-18
Logical Data Model Approved
Data Model · Amina Zayed
Completed
2026-06-012026-06-12
Cadastral Layer Migration Complete
Data Migration · Rami Haddad
Delayed
2026-09-152026-09-30
Field Mobile App UAT
Application Development · Lina Serhan
Not Started
2026-11-102026-11-10
Platform Deployment Approval
Platform & Infrastructure · Yousef Rahman
Not Started
2027-02-202027-02-20

RAID Exposure

3 open items

Cadastral duplicate parcels exceed cleansing capacity
Risk · Data Quality · Rami Haddad
Critical
Topology gaps on utilities network after projection conversion
Issue · Spatial Accuracy · Nadia Osman
High
Municipality address gazetteer refresh required
Dependency · Integration · Yousef Rahman
Medium

Recent Activity

Raised spatial quality issue GISS-003 on Utilities MV layer
Nadia Osman · 2026-09-01 15:10
Cadastral migration cycle 3 loaded — 96.4% attribute completeness
Rami Haddad · 2026-08-31 10:02
Published spatial layer LYR-Cadastral-Parcels to SIT
Amina Zayed · 2026-08-28 13:44