Enterprise Data Migration Program
ETP-2026-006 · IT Implementation · Hybrid · Doha, Qatar
Sponsor Omar SiddiquiPM Sara IdrissiPMO Group PMO — Omar SiddiquiImplementation Partner Meridian ConsultingDates 2026-05-04 → 2027-08-31Budget QAR 9.60 M
Data MigrationNext gate: Requirements Sign-offAMBER
Completion
21%
Planned 24%
Phase
Data Migration
Next gate Requirements Sign-off
Forecast vs Budget
QAR 9.60 M
Approved QAR 9.60 M
Pending Approvals
2
Open Risks
5
0 critical
Resource Utilisation
70%
Completion
21%
Requirements Approved
62%
Test Pass Rate
0%
Critical Defects
0
Integrations Live
18%
Cutover Readiness
5%
Phase Progress
Planned vs actual by lifecycle phase
Progress Curve
Planned, actual and forecast %
Stage Gate Timeline
Milestone Performance
RAID Exposure
0 open items