Cybersecurity Infrastructure Upgrade
ETP-2026-004 · IT Implementation · Hybrid · Doha, Qatar
Sponsor Omar SiddiquiPM Zeina KhouryPMO Group PMO — Omar SiddiquiImplementation Partner NetShield TechnologiesDates 2026-04-06 → 2027-02-26Budget QAR 14.80 M
Build & ConfigurationNext gate: SIT ReadinessAMBER
Completion
52%
Planned 50%
Phase
Build & Configuration
Next gate SIT Readiness
Forecast vs Budget
QAR 15.40 M
Approved QAR 14.80 M
Pending Approvals
3
Open Risks
6
1 critical
Resource Utilisation
82%
Completion
52%
Requirements Approved
88%
Test Pass Rate
71%
Critical Defects
2
Integrations Live
44%
Cutover Readiness
20%
Phase Progress
Planned vs actual by lifecycle phase
Progress Curve
Planned, actual and forecast %
Stage Gate Timeline
SIT Readiness
Planned 2026-10-16
1/2Pending
Milestone Performance
Zero-trust design approved
Solution Architecture · Zeina Khoury
Completed
2026-06-19 → 2026-06-24
SIEM Migration Complete
Infrastructure · Bilal Nasser
In Progress
2026-09-18 → 2026-09-25
Privileged access rollout
Security · Zeina Khoury
Not Started
2026-11-27 → 2026-11-27
RAID Exposure
1 open items
Legacy VPN concentrators unsupported after vendor EOL
Risk · Technical · Bilal Nasser