New Administrative Building Project
ETP-2026-005 · Construction Project · Stage-gate · Lusail, Qatar
Sponsor Ahmed Al RashidPM Ibrahim DohaPMO Group PMO — Omar SiddiquiContractor Al Bidda ContractingDates 2026-02-15 → 2028-06-30Budget QAR 365.00 M
Under ConstructionNext gate: BCC — Building CompletionAMBER
Completion
27%
Planned 31%
Phase
Under Construction
Next gate BCC — Building Completion
Forecast vs Budget
QAR 368.50 M
Approved QAR 365.00 M
Pending Approvals
6
Open Risks
8
0 critical
Resource Utilisation
79%
SPI
0.92
CPI
1.01
Physical Progress
27%
Open NCRs
11
Open RFIs
13
Cost Variance
QAR -3.50 M
Phase Progress
Planned vs actual by lifecycle phase
Progress Curve
Planned, actual and forecast %
Stage Gate Timeline
Execution Start
Planned 2026-04-30
2/2Approved
BCC — Building Completion
Planned 2028-04-30
0/2Pending
Milestone Performance
Enabling works complete
Civil & Structural · Ibrahim Doha
Completed
2026-05-30 → 2026-06-10
Structure to L8
Civil & Structural · Al Bidda Contracting
Delayed
2026-09-28 → 2026-10-12
MEP first fix — L1–L4
MEP Works · Sami Aziz
Not Started
2027-01-20 → 2027-01-20
RAID Exposure
1 open items
Façade package procurement lead time exceeds programme float
Risk · Procurement · Ibrahim Doha